The project stores electric energy during off-peak and valley price periods, and uses stored energy to replace part of the public grid power supply for the owner during critical peak and peak price periods, so as to reduce electricity costs.
The new energy storage system will be built within the red line on the north side of the factory area, on the vacant land to the north of Plant 2 and west of the waste room.
Energy storage batteries, BMS, EMS, PCS, fire protection system, lighting and other equipment are integrated into a 25-foot integrated container, forming an indoor energy storage power station with a capacity of 250 kW / 1,000 kWh.